Project name: Implementation of a sewage network in Sokhna camp

Project justification:

  1. Sokhna camp which is located in Zarqa Governorate, is not served by a sewage network and the wastewater is discharged through cesspits
  2. The presence of more than one cesspit under some houses it became a serious danger to some houses and their residents
  3. The land soil of the camp has become saturated with water Sanitary drainage
  4. The foundations of some very old houses that was built since the camp was established in 1969 may be affected
  5. The high financial cost for the camp’s residents resulting from periodically draining these cesspits increases the financial burden on them
  6.  the need for this project is urgent in order to preserve the safety of the residents the camp

Project elements:

  1.  Implementation of sewage networks with an approximate length of 85 km
  2. Implementation of transmission lines with an approximate length of 17 km
  3. Create a lifting station within the Sanitation Program: NEXUS

 

Suggested projects for 2021

First: social safety package projects

Housing Rehabilitation Project/12

#

Camp

Suggested project

Estimated cost/JD

1

Baqa camp

Rehabilitation of 15 units

150000

2

Hitteen Camp

Rehabilitation of 10 units

100000

3

Zarqa Camp

Rehabilitation of 5 units

50000

4

Souf Camp

Rehabilitation of 5 units

50000

5

Irbid Camp

Rehabilitation of 5 units

50000

TOTAL

Rehabilitation of 40 units

400000

 

Second: Royal Initiatives

#

Camp

Suggested project

Estimated cost/JD

1

Baqa camp

Building a kindergarten for the women’s program center

40000

2

Prince Hassan Camp

Rehabilitation of units

45000

3

Martyr Azmi Al-Mufti Camp

Rehabilitation of the valley by constructing a canal to drain rainwater

300000

4

Souf camp

Reconstruction of the women's program center headquarters within an area of 50 m2

20000

5

Prince Hassan Camp

Construction of an investment building for the camp committee service benefit

100000

6

Jerash Camp

Create the garden in the forest of Jerash

100000

7

Al-Wihdat Camp

 The hall,

Committee offices and a garden

350000

8

Zarqa Camp

Maintenance of Al- Al Awdeh Youth Club playground

30000

9

Irbid Camp

Construction of a gym, Al-Jalil Youth Club

250000

10

Al-Hussein Camp

Adding classrooms to the kindergarten

And Disability department with an area of 95 m2

Maintenance of the building with an area of 347 m2

100000

 

Third: Camp Services Committees Projects

Executing several projects and conducting the necessary maintenance to maintain the sustainability of the infrastructure, such as the maintenance of asphalt roads, concrete corridors and rainwater drainage.

at a value of 400,000 JD,