Establishing headquarters for civil society organizations in the camps
A set of headquarters for civil society organizations have been built in the camps, as follows:
1- Construction of a civil society organizations building in Baqa ’a camp:
Project description: The project consists of (8) headquarters with an area of (550) m2
Implementing party: Department of Palestinian Affairs
Estimated cost: 150,000 dinars
Implementation date: 2020
2- Construction of a civil society organizations building in Baqa ‘a camp:
Project description: The project consists of (8) headquarters with an area of (900) m2
Implementing party: Department of Palestinian Affairs
Estimated cost: 244,000 dinars
Implementation date: 2016-2017
3- Construction of a civil society organizations building in Al-Wihdat camp:
Project description: The project consists of (8) headquarters with an area of (850) m2
Implementing party: Ministry of Public Works
Estimated cost: 325,000 dinars
Implementation date: 2014-2015