Development centers and investment buildings
1- Constructing a Hall & administration offices in Al Wihdat Camp
Project description: The project consists of two floors (Ground floor & 1st floor) and a hall with area of (930 m2)
Implementing party: Department of Palestinian Affairs
Estimated cost: 400000 JD
Implementing date: 2022-2023
2- Constructing an investment building for Talbieh Camp Services Committee:
Project description: The project consists of the following:
- Ground floor – consisting of a commercial stores with five doors on the main street with an area of (478 m2) and high of (6 m2) served by stairs and elevators.
- 1st floor consisting of offices, meeting room, cafeteria and a bathroom with an area of (487 m2).
The building was constructed according to the general safety rules.
Implementing party: Department of Palestinian Affairs
Estimated cost: 475000 JD
Implementing date: 2021-2022
3- Constructing an Investment Building for Prince Hassan Camp Services Committee:
Project description: The project consists of the following:
- Basement floor consisting of 4 stores with an area of (85m2)
- Ground floor consisting of 4 stores with an area of (100 m2)
- 1st floor consisting of a hall for Camp Service Committee, Cafeteria and a bathroom with an area of (100 m2)
Implementing party: Department of Palestinian Affairs
Estimated cost: 100000 JD
Implementing date: 2021
4- Constructing an investment building for Irbid Camp Services Committee:
Project description: The project consists of (18) stores with a total area of (850 m2).
Implementing party: Department of Palestinian Affairs
Estimated cost: 250,000 JD
Implementation date: 2020-2021

5- Constructing a comprehensive development center for Souf Camp Services Committee:
Project description: The project consists of a multi-purpose hall, offices and services with an area of 800 m2, stores with an area of 200 m2, and maintenance of the playground in the camp garden with an area of 1000 m2.
Implementing party: Department of Palestinian Affairs
Estimated cost: 400,000 JD
Implementation date: 2019-2021


6- Constructing a comprehensive development center for Hitteen Camp Services Committee:
Project description: The project consists of a multi-purpose hall and administrative offices with an area of 960 m2 and stores with an area of 185 m 2
Implementing party: Department of Palestinian Affairs
Estimated cost: 408000 JD
Implementation date: 2016


7- Completion of the comprehensive development center in Baqa ‘a camp:
Project description: It consists of an extension to the public service office on the ground floor, administrative offices, meeting rooms and the department office on the first floor with a total area of 870 m
Implementing party: Department of Palestinian Affairs
Estimated cost: 258000 JD
Implementation date: 2016

8- Constructing a comprehensive development center for Zarqa Camp Services Committee:
Project description: The project consists of a hall for events on the ground floor serving the people of the camp, a multi-purpose hall, administrative offices for the Camp Services Committee and the department office on the first and second floors with a total area of 1200 m2
Implementing party: Department of Palestinian Affairs
Estimated cost: 294,000 JD
Implementation date 2016

9- Constructing a building for Al-Hussein Camp Services Committee and Al-Hussein Youth Club:
Project description: The project is a joint building consisting of two headquarters for the Camp Services Committee and Al-Hussein Youth Club, with an area of 1000 m2
Implementing party: Ministry of Public Works
Estimated cost: 528000 JD
Implementation date 2016

10- Constructing a hall for Martyr Azmi Al-Mufti Camp Services Committee:
Project description: The project consists of a multi-purpose hall, and health facilities with an area of 617 m2
Implementing party: Department of Palestinian Affairs
Estimated cost: 247000 JD
Implementation date: 2016

11- Constructing a comprehensive development center in Baqa ’a camp:
Project description: It consists of a multi-purpose hall, committee offices, and health facilities with an area of 1130 m2
Implementing party: Governmental Buildings Department
Estimated cost: 522000 JD
Implementation date 2013-2015

12- Constructing an investment building for Jerash Camp Services Committee:
Project description: It consists of a multi-purpose hall, committee offices, and health facilities with an area of 990 m2
Implementing party: Governmental Buildings Department
Estimated cost: 340,000 JD
Implementation date: 2013-2015

13- Constructing a hall for Irbid camp services committee:
Project description: It consists of a multi-purpose hall, and health facilities with an area of 470 m2
Implementing party: Governmental Buildings Department
Estimated cost: 207000 JD
Implementation date: 2013

14- Constructing an investment building for Talbieh Camp Services Committee:
Project description: It consists of a multi-purpose hall, health facilities with an area of 1160 m2
Implementing party: Department of Palestinian Affairs
Estimated cost: 223,000 JD
Implementation date: 2013

15- Constructing a comprehensive development center for Madaba Camp Services Committee:
Project description: It consists of two floors, stores on the ground floor and part of the first floor with an area of 775 m2
Implementing party: Governmental Buildings Department
Estimated cost: 289,000 JD
Implementation date: 2012

16- Constructing an investment building for Hitteen Camp Services Committee (first floor):
Project description: The project consists of a multi-purpose hall and offices for the Department and the Services Committee with an area of 1,000 m2
Implementing party: Department of Palestinian Affairs
Estimated cost: 150,000 JD
Implementation date: 2007

17- Constructing an investment building for Prince Hassan Camp Services Committee:
Project description: It consists of two floors (basement and ground floor) and stores with an area of 1000 m2.
Implementing party: Ministry of Public Works and Housing
Estimated cost: 290,000 JD
Implementation date: 2007