   1- Constructing a Hall & administration offices in Al Wihdat Camp

   Project description: The project consists of two floors (Ground floor & 1st floor) and a hall with area of (930 m2)

   Implementing party: Department of Palestinian Affairs

   Estimated cost: 400000 JD

   Implementing date: 2022-2023

 

   2- Constructing an investment building for Talbieh Camp Services Committee:

   Project description: The project consists of the following:

   - Ground floor – consisting of a commercial stores with five doors on the main street with an area of (478 m2) and high of (6 m2) served by stairs and elevators.

   - 1st floor consisting of offices, meeting room, cafeteria and a bathroom with an area of (487 m2).

   The building was constructed according to the general safety rules.

   Implementing party: Department of Palestinian Affairs

   Estimated cost: 475000 JD

   Implementing date: 2021-2022

 

   3- Constructing an Investment Building for Prince Hassan Camp Services Committee:

   Project description: The project consists of the following:

   - Basement floor consisting of 4 stores with an area of (85m2)

   - Ground floor consisting of 4 stores with an area of (100 m2)

   - 1st floor consisting of a hall for Camp Service Committee, Cafeteria and a bathroom with an area of (100 m2)

   Implementing party: Department of Palestinian Affairs

   Estimated cost: 100000 JD

   Implementing date: 2021

 

4- Constructing an investment building for Irbid Camp Services Committee:

Project description: The project consists of (18) stores with a total area of ​​ (850 m2).

Implementing party: Department of Palestinian Affairs

Estimated cost: 250,000 JD

Implementation date: 2020-2021

 

5- Constructing a comprehensive development center for Souf Camp Services Committee:

Project description: The project consists of a multi-purpose hall, offices and services with an area of ​​800 m2, stores with an area of ​​200 m2, and maintenance of the playground in the camp garden with an area of ​​1000 m2.

Implementing party: Department of Palestinian Affairs

Estimated cost: 400,000 JD

Implementation date: 2019-2021

 

6- Constructing a comprehensive development center for Hitteen Camp Services Committee:

Project description: The project consists of a multi-purpose hall and administrative offices with an area of ​​960 m2 and stores with an area of ​​185 m 2

Implementing party: Department of Palestinian Affairs

Estimated cost: 408000 JD

Implementation date: 2016

 

7- Completion of the comprehensive development center in Baqa ‘a camp:

Project description: It consists of an extension to the public service office on the ground floor, administrative offices, meeting rooms and the department office on the first floor with a total area of ​​870 m

Implementing party: Department of Palestinian Affairs

Estimated cost: 258000 JD

Implementation date: 2016

 

8- Constructing a comprehensive development center for Zarqa Camp Services Committee:

Project description: The project consists of a hall for events on the ground floor serving the people of the camp, a multi-purpose hall, administrative offices for the Camp Services Committee and the department office on the first and second floors with a total area of ​​1200 m2

Implementing party: Department of Palestinian Affairs

Estimated cost: 294,000 JD

Implementation date 2016

 

9- Constructing a building for Al-Hussein Camp Services Committee and Al-Hussein Youth Club:

Project description: The project is a joint building consisting of two headquarters for the Camp Services Committee and Al-Hussein Youth Club, with an area of ​​1000 m2

Implementing party: Ministry of Public Works

Estimated cost: 528000 JD

Implementation date 2016

 

10- Constructing a hall for Martyr Azmi Al-Mufti Camp Services Committee:

Project description: The project consists of a multi-purpose hall, and health facilities with an area of ​​617 m2

Implementing party: Department of Palestinian Affairs

Estimated cost: 247000 JD

Implementation date: 2016

 

11- Constructing a comprehensive development center in Baqa ’a camp:

Project description: It consists of a multi-purpose hall, committee offices, and health facilities with an area of ​​1130 m2

Implementing party: Governmental Buildings Department

Estimated cost: 522000 JD

Implementation date 2013-2015

 

12- Constructing an investment building for Jerash Camp Services Committee:

Project description: It consists of a multi-purpose hall, committee offices, and health facilities with an area of ​​990 m2

Implementing party: Governmental Buildings Department

Estimated cost: 340,000 JD

Implementation date: 2013-2015

 

13- Constructing a hall for Irbid camp services committee:

Project description: It consists of a multi-purpose hall, and health facilities with an area of ​​470 m2

Implementing party: Governmental Buildings Department

Estimated cost: 207000 JD

Implementation date: 2013

 

14- Constructing an investment building for Talbieh Camp Services Committee:

Project description: It consists of a multi-purpose hall, health facilities with an area of ​​1160 m2

Implementing party: Department of Palestinian Affairs

Estimated cost: 223,000 JD

Implementation date: 2013

 

15- Constructing a comprehensive development center for Madaba Camp Services Committee:

Project description: It consists of two floors, stores on the ground floor and part of the first floor with an area of ​​775 m2

Implementing party: Governmental Buildings Department

Estimated cost: 289,000 JD

Implementation date: 2012

 

16- Constructing an investment building for Hitteen Camp Services Committee (first floor):

Project description: The project consists of a multi-purpose hall and offices for the Department and the Services Committee with an area of ​​1,000 m2

Implementing party: Department of Palestinian Affairs

Estimated cost: 150,000 JD

Implementation date: 2007

 

17- Constructing an investment building for Prince Hassan Camp Services Committee:

Project description: It consists of two floors (basement and ground floor) and stores with an area of ​​1000 m2.

Implementing party: Ministry of Public Works and Housing

Estimated cost: 290,000 JD

Implementation date: 2007